Nvidia Loan Guarantees for OpenAI’s Ohio Campus Start Only When Each Building Is Ready for Service

Nvidia’s third-quarter filing spells out that its data center guarantees switch on only after construction is finished, so the risk of a stalled build stays with the builder and its lenders.

Line-art illustration of a row of data center buildings where only the completed ones carry a guarantee seal, representing Nvidia loan guarantees that start when each building is ready

Nvidia loan guarantees for AI data centers do not cover the construction phase. In its CFO commentary for the third quarter of fiscal 2027, published November 17, 2026, Nvidia says the guarantee backing OpenAI’s PORTS-Pike campus in Ohio takes effect one building at a time, only when each building is complete and ready for service, with the first expected in fiscal 2029.

Nvidia Loan Guarantees for PORTS-Pike Take Effect One Building at a Time

In August 2026, Nvidia agreed to provide credit support for the land, power and shell buildout of roughly 4.25 gigawatts across nine buildings at SB Energy’s PORTS-Pike Technology Campus in Ohio. Under the deal, the campus will host only Nvidia infrastructure, leased to OpenAI on 20-year terms with limited exceptions. The CFO commentary says Nvidia’s exposure grows as each building comes online, peaks at $105 billion, and then shrinks over each lease term as OpenAI pays rent. Nvidia also holds an option to extend credit support to about 3.8 more gigawatts in phases as the site grows. The company says it has made no payments under any of its guarantees so far.

Nvidia’s Total Guarantee Exposure Reached $118 Billion at the End of October

Nvidia put its maximum gross guarantee exposure at $118.0 billion as of October 25, 2026, the last day of the quarter. PORTS-Pike accounts for $105.0 billion of that. Another $9.5 billion is credit support for power and systems, and $3.5 billion covers land, power and shell guarantees for neoclouds. The same commentary lists $518 billion in total future commitments, made up of $390 billion for supply and capacity, $74 billion in data center leases that have not yet started, $28 billion in cloud service agreements, $20 billion in equity investments and $6 billion in capital expenditure. Separate commitments under neocloud agreements total $32 billion.

Neocloud Commitments Depend on Financing, Deployment and Nvidia’s Own Acceptance

Nvidia’s commitments to neoclouds carry three conditions. The neocloud has to secure financing to buy the infrastructure, the compute has to be deployed and running, and Nvidia has to accept it. The commentary says the $32 billion figure assumes all of those conditions are met, and that commitments could be reduced or eliminated if they are not resolved in time. Nvidia frames the program as a response to customers whose growth has outrun their balance sheets and credit profiles. In return, it earns revenue on the upfront hardware sale and, when certain criteria are met, a share of the revenue neoclouds collect from their own customers.

Colette Kress Called the Terms a Clarification of Existing Policy

On the earnings call on November 17, interim CEO and CFO Colette Kress walked analysts through the sequence. The customer raises capital, builds and readies the site, and procures and installs the compute, and only then does Nvidia’s guarantee start. If the build is delayed or runs into trouble before that point, she said, “our guarantee doesn’t exist anymore.” TechCrunch’s Julie Bort reported that Kress described this as a clarification of existing terms, and that those terms had not been disclosed publicly before. Kress also told analysts Nvidia would be more selective about which companies it helps finance. The disclosures came alongside quarterly revenue of $115.8 billion and GAAP net income of $65.3 billion, according to Nvidia’s results release. The commentary adds that Nvidia plans to file its fuller 10-Q report in the coming weeks.

Why This Matters for Engineering Leadership

If your company reserves GPU capacity from a neocloud or a lab-adjacent data center project, Nvidia’s terms tell you where the delivery risk sits. The vendor backstop starts after a building is finished and its compute is accepted, so the stretch where projects most often slip, financing and construction, is carried by the provider and its lenders alone. A capacity contract for a building that is not yet in service is a bet on that provider’s financing. Before signing, ask the provider which of your reserved capacity is already running, which depends on financing it has not closed, and what your contract says about credits, alternative capacity or exit rights if a building slips. Treat a vendor guarantee in a provider’s pitch as a statement about finished buildings, because that is what Nvidia’s own filing says it covers.

FAQ

When does Nvidia’s PORTS-Pike loan guarantee take effect?

Building by building. Each guarantee becomes effective only when its related building is completed and ready for service, and Nvidia expects the first in fiscal 2029.

How large is Nvidia’s guarantee for OpenAI’s Ohio campus?

Nvidia’s exposure can reach a maximum of $105 billion, then declines over each 20-year lease term as OpenAI makes lease payments.

What is Nvidia’s total guarantee exposure?

Nvidia reported maximum gross guarantee exposure of $118.0 billion at October 25, 2026, including $105.0 billion for SB Energy, $9.5 billion for power and systems, and $3.5 billion for neoclouds.

Has Nvidia paid anything under its data center guarantees?

No. The CFO commentary says Nvidia has not made any payments related to its guarantees to date.

What conditions apply to Nvidia’s neocloud commitments?

They take effect only if the neocloud secures financing to buy the infrastructure and the compute is deployed, operational and accepted by Nvidia. Otherwise they can be reduced or eliminated.

Source: Nvidia clarifies when it will — and won’t — keep financing neoclouds by Julie Bort, TechCrunch, November 18, 2026. Primary source: Nvidia CFO Commentary on Third Quarter Fiscal 2027 Results, filed with the SEC on November 17, 2026.